HDD FOR CROSS RIVER AT JAMBATAN AYER ITAM, PENANG

HDD Jambatan ayer itam
HDD Jambatan ayer itam 2
Project Overview

Teraband Smart Solution Sdn Bhd has successfully completed a highly challenging Horizontal Directional Drilling (HDD) project at Jambatan Ayer Itam, Penang. The project involved crossing a river with a total HDD length of 150 meters and a maximum depth of 21 meters, demonstrating Teraband’s unmatched technical capabilities and precision engineering in addressing complex infrastructure requirements.

Advanced Methodology and Equipment

The project utilized advanced HDD machinery (OS35T) to navigate the challenging geological conditions while ensuring minimal environmental disruption. To achieve precise tracking and alignment during the drilling process, Teraband integrated cutting-edge technologies, including the HDD Locator 7T and Locator GL750, which provided real-time monitoring and enhanced accuracy throughout the operation. These tools allowed the team to overcome obstacles posed by varying soil layers and maintain borehole stability under high hydrostatic pressure.

Additionally, Teraband installed a combination of 200mm x 12 numbers + 110mm x 6 (4 circuits) PN10 HDPE red pipe in multi-circuit configurations. This setup was specifically designed to cater to the unique demands of the 132kV power cable installation. Furthermore, our use of advanced mandrel tests and gyroscope mapping tests ensured precise alignment and exceptional durability, demonstrating our capability to manage complex and demanding projects effectively.

The Challenges 

This project involves significant challenges due to the intricate nature of constructing the bridge and the complexities of the river environment. The geological and soil conditions are particularly demanding, as the riverbed comprises a substantial amount of sand, which increases the risk of instability and sinking during foundation and concrete work. These conditions also critically impact the success of Horizontal Directional Drilling (HDD) operations, as sandy substrates can lead to borehole collapse, fluid loss, and difficulty in maintaining bore stability. Furthermore, the high hydrostatic pressure under the river adds to the challenge, requiring precise pressure management to prevent borehole collapse and drilling fluid leakage. Additionally, maintaining consistent piloting signals in this environment presents another layer of difficulty. The shifting sands can disrupt signal accuracy, complicating the navigation of the drill and potentially leading to deviations in the bore path.  

Overcoming Challenges

Despite the numerous challenges associated with HDD for cross-river projects, our engineering team’s meticulous planning and execution were key to overcoming these obstacles and ensuring the project’s success. To manage the challenges of geological and soil conditions, we utilized advanced equipment, such as specialized drill heads and reamers, to stabilize the borehole and effectively navigate the riverbed. Our team also employed innovative solutions, including mandrel testing and gyroscope mapping, to maintain precise alignment and ensure bore durability throughout the process. In tackling high hydrostatic pressure, we implemented pressure control techniques to prevent fluid loss and borehole collapse. By combining technical expertise with cutting-edge technology and proactive problem-solving, our team successfully overcame these hurdles, delivering a stable and efficient cross-river project that adhered to both engineering standards and environmental protection requirements.

Industry Leadership

The successful execution of the Jambatan Ayer Itam project underscores Teraband’s expertise and reliability in delivering technically demanding projects that many others would find difficult to execute. It stands as a testament to their ability to combine advanced technology, skilled personnel, and a commitment to sustainability to meet Malaysia’s growing infrastructure needs.

Completed Project

No
Site Name
Length
HDD & Civil Scope
Project Owner
1
Perindustrian Tasek
OSP for 5775 Meter
  • 1800 Meter Open Cut
  • 3975 Meter HDD
  • 5 Pedestal
  • 1 FDC Cabinet
MAXIS
2
Coventya (Maxis Enterprise OPS+ISP), JOHOR

OSP for 200 Meter ISP for 350 Meter

 

  • Install 6 ports Fiber Module
  • Splicing & Testing
  • Fiber puling cable
MAXIS
3Bakar Arang, KEDAHHDD 655 Meter
  • Helping existing Contractor to solve the problem
  • Installation of manhole and PN10 for Manhole lead‐in
  • Open Cut and Road Pavement
MAXIS
4

Clarivate (TDC Enterprise), PENANG

 

HDD 160 Meter + Civil Works
  • 4” PN10 2ways with Sub‐duct
  • Installation of manhole, premix tar
  • at premise and backfilling.
TIMEDOTCOM
5UGC Segamat TNB 132kV, JOHORCompleted HDD 660 Meter
  • 8 ways (2 Circuit)
  • 6 x 4 ways
  • 4 x 4 ways
TENAGA NASIONAL BERHAD
6UGC Ampang TNB 132kV, KUALA LUMPURCompleted HDD 2360 Meter
  • 8 ways (2 Circuit)
  • 10 x 6 ways
  • 4 x 2 ways
TENAGA NASIONAL BERHAD
7UGC Ampang TNB 132kV, KUALA LUMPURIn progress HDD 600 Meter
  • 8 ways (2 Circuit)
  • 10 x 6 ways
  • 4 x 2 ways
TENAGA NASIONAL BERHAD
8

Celcom Micro‐duct, PERAK

  • Gopeng
  • Teluk Intan
  • Tanjung Bidara

Completed HDD 5142 Meter

Micro‐ductCELCOM
9PAKO, KUALA LUMPUR

Completed OSP 1600 Meter

  • 2 Ways 4 Inch Pipe
  • 4 Ways 32mm2 Subduct
  • Installation of Manhole

U Mobile

10

PAKO, KUALA LUMPUR

In progress OSP 1200 Meter

  • 2 Ways 4 Inch Pipe
  • 4 Ways 32mm2 Subduct
  • Installation of Manhole

U Mobile

Showcasing Excellence in Completed Projects: The Expertise of HDD and Open-Cut Contractors in Malaysia

Teraband stand out for their expertise in completing diverse and challenging projects. From directional drilling to open-cut excavation, their portfolio highlights the crucial role of HDD contractors and open-cut contractors in Malaysia. Each project serves as a testament to the importance of these methods in delivering efficient, reliable, and environmentally conscious solutions.

The Importance of Completed Projects in Infrastructure Development

Completed projects provide insight into a contractor’s technical expertise and reliability. They are a benchmark for assessing the quality of work, adherence to timelines, and the ability to overcome site-specific challenges. In Malaysia, the demand for contractors skilled in both directional drilling and open-cut excavation has surged due to the need for sustainable infrastructure solutions.

Notable Completed Projects Utilizing Directional Drilling

Directional drilling, also known as Horizontal Directional Drilling (HDD), is widely recognized for its ability to install underground pipelines and cables without extensive surface excavation. In urban centers and environmentally sensitive areas, HDD is the preferred method for preserving landscapes and maintaining traffic flow.

One standout project involves the installation of underground pipelines beneath heavily trafficked areas. By employing advanced HDD techniques, Teraband ensured the pipelines were laid without disrupting daily activities or causing damage to the surrounding infrastructure. The success of this project highlights the importance of skilled HDD contractors in Malaysia’s urban infrastructure development.

Open-Cut Excavation Projects: Building a Strong Foundation

While HDD is ideal for specific conditions, open-cut excavation remains a fundamental approach in projects requiring direct access to underground utilities. As a leading open-cut contractor in Malaysia, Teraband has executed numerous large-scale projects that underscore the importance of this traditional method. In another project, open-cut methods were used to install water distribution pipelines in a rural area. This method proved effective in creating a reliable water supply system while maintaining cost-efficiency. The meticulous planning and execution involved in this project illustrate the essential role of open-cut contractors in Malaysia’s rural development efforts.

The Synergy of HDD and Open-Cut Methods

Many of Teraband’s completed projects involve a combination of directional drilling and open-cut excavation. For example, in a comprehensive utility installation project, HDD was employed to navigate under roadways and environmentally sensitive areas, while open-cut excavation was used for sections requiring direct access. This integrated approach ensured the project met all functional and regulatory requirements while minimizing environmental impact.